Veolia Energie - Documentation for 2 x 20 MW hot water gas boiler room

Documentation for a joint zoning and building permit for a hot water gas boiler room with a 2 x 20 MW input in the Veolia power plant complex in Trebovice.

The scope of the processed documentation included preparation of all required documents, i.e. documents for administrative proceedings and permit processing from the relevant state administration bodies and network administrators, including incorporation of comments from the concerned parties, for implementation of the investment project.

As part of the contract, IVITAS designers also prepared documentation related to activities that could be potentially carried out on the buildings - liquidation, demolition work and alterations.

 

Client: Veolia Energie CR, a.s.

Location: Veolia power plant Trebovice, Czech Republic

Implementation: 2021